Batch Planning
Batch Criteria
- Same Garment Type: All 11oz mugs, all medium t-shirts, etc. Different sizes = different setup time.
- Similar Color: Group light designs together, dark designs together. Changing curing temperature adds setup time.
- Related Process: All pretreatment, all DTG print, all heat-press cure. Don't mix process stages.
- Common Tools: All designs using same template or setup reduce retooling.
Batch Sizing Strategy
- Small Batches (5–10 units): For custom or rush orders. Setup time is significant fraction of total production time.
- Medium Batches (20–50 units): Most efficient for small shops (1–2 presses). Setup overhead amortized well.
- Large Batches (100+ units): Ideal for high-volume production. Setup time becomes negligible per unit.
- Queue Optimization: Plan 2–3 batches per day so setup time is only 15–20% of total.
Pre-Production Setup
1. Sort and Stage Work
- Collect all garments for the batch; count and verify quantity.
- Arrange by color if possible (light → medium → dark).
- Lay out all design files on desktop; verify all are production-ready.
- Pre-heat press and curing station 20–30 minutes before start.
2. Configure Machines
- For DTG: Load garment size and pretreatment settings; test print on scrap garment.
- For Screen Printing: Mount screen; adjust squeegee pressure; flood pass to verify ink flow.
- For Heat Press: Set temperature, pressure, and dwell time; verify with test garment.
- Document Settings: Write down all parameters on production sheet for consistency.
3. Prepare Materials
- DTG: Load paper into pretreatment sprayer; fill ink reservoirs if running low.
- Screen Printing: Mix ink to correct viscosity; add to screen coating station.
- Heat Press: Lay out blank garments near press in sequential order.
Production Sequencing
**Phase 1: Pretreatment** (if DTG)
- Load first 10 garments into spray booth.
- Spray evenly; send through conveyor dryer.
- Stack treated garments on cart; keep warm.
- Repeat until all garments treated.
**Phase 2: Printing**
- Load first pretreated garment onto print bed.
- Print design; verify print position and quality.
- If acceptable, continue with remaining garments.
- Queue printed garments for curing.
**Phase 3: Curing**
- Transfer printed garments to heat press or curing conveyor immediately.
- Cure per specification.
- Remove and cool on rack.
- Stack onto final pallet.
**Phase 4: Quality Check and Packaging**
- Inspect every 10th garment; check color, registration, and adhesion.
- Fold and bag completed garments.
- Label with order number and date.
- Stage for shipping.
Efficiency Metrics
Production Rate = Total garments completed / Total time (including setup)
- Target: 10–20 units/hour for small shops; 30–50+ for industrial automation
- Track by batch to identify bottlenecks
Setup Time % = Setup time / (Setup + Production time) × 100
- Ideal: 15–20% for batches of 20+ units
- Above 30%: Batch too small or process too complex; combine with next batch
Quality Rate = Accepted units / Total units completed × 100
- Target: > 95%
- Below 95%: Investigate curing, pretreatment, or machine calibration issues
Utilization Rate = Productive time / Available shift time × 100
- Target: 70–80% (includes break time, setup, QC)
- Below 70%: Machine idle time or scheduling inefficiency
Nesting and Waste Reduction
For Print-and-Cut (Sublimation, UV DTF)
- Arrange designs on film/paper to minimize waste
- Rotate small designs to fill gaps
- Target: < 10% waste per sheet
For Screen Printing
- Use half-screens for small designs
- Nest multiple small designs on one screen
- One-color designs on shared screens to save screen inventory
For DTG on Garments
- Position design 3–4 inches from collar and sleeves
- Consistent placement across batch for smooth operation
Scheduling and Workload Balancing
Daily Schedule Example (3 batches, 8-hour shift)
- 7:00–7:30 AM: Setup; warm machines
- 7:30–9:00 AM: Batch 1 (30 units of design A)
- 9:00–9:30 AM: Setup Batch 2
- 9:30–11:00 AM: Batch 2 (25 units of design B)
- 11:00–11:15 AM: Lunch + Setup Batch 3
- 11:15–1:00 PM: Batch 3 (40 units of design C)
- 1:00–3:00 PM: QC and packaging; prep tomorrow's batches
- 3:00–5:00 PM: Shift end; cool and clean machines
Capacity Planning
- Identify your bottleneck (usually heat press or printer)
- Schedule batches to keep bottleneck machine busy 70–80% of shift
- Use secondary equipment (second heat press, second printer) to run parallel batches
Common Batching Issues
Inconsistent Results Between Batches: Different operators, curing temperatures, or settings. Document all parameters; enforce consistency through checklists.
Batch Larger Than Needed: Order smaller batches to test before committing to full run. Reduces risk of high-volume defects.
Too Many Setups: Batch too small. Group with nearby batches or reschedule for higher efficiency.
Machine Downtime During Batch: Inadequate pre-production checks. Test print before loading full batch.